EME 06 Launch of software project
Launch of software project
- Recruiting the Project Team
- Team Operating Rules
- Problem Solving
- Decision Making
- Conflict Resolution
- Consensus Building
- Brainstorming
- Team Meetings
- Scope change management process
- Communications management planning
- Work packages
- Resource assignment
- Finalize the project schedule
project charter

Scope Change Management
typical process

Project Impact Statement
- What is the expected benefit of the change?
- How would the change affect the project’s cost?
- How would the change affect the project’s schedule?
- How would the change affect the software’s quality?
- How would the change affect the project’s resource allocation?
- Can the change be deferred to a later stage of the project or a later version of the software?
- Is the project at a point when making the change would risk destabilizing the software?
Scope Change Request Form

Management Reserve
A percentage (5-10%) of the project duration is set aside as a time contingency for processing and incorporating scope change requests.
Set up a scope request bank account with an initial deposit of time (5-10 percent of total project work time) to be used to process cope changes and adjust the schedule.
Communications Management
RASCI Matrix

Expanded Variation

Work Packages
A Work Package is a brief description at the subtask level that describes how a task will be completed. It is a primitive(初始) project plan.