PROJECT FORECAST SCHEDULE

PROJECT FORECAST SCHEDULE

1. Idea finalize
Target Marketing
1st week
2. Rough drawing - appearance 3rd week
3. Customer feedback 4th week
4. Latest design drawing done 5th week
5. Customer approval - cosmetic
Tooling quotation and option
6-7th week
6. Unit price quotation and negotiation
Material
Speaker spec.
7th week
7. Tooling P.O. issued from customer
P.P. order
Set up tooling schedule
1st shot (not texture)
2nd shot
8th week
8. Detail drawing and M.P. order
Bty carton
NW
9th week
9. Customer send artwork
Ctn box and owners manual
Warranty card and w/logo
12-14th week
10. 1st sample after tooling done 16-17th week
11. 2nd final sample
Accoustic approval
17-18th week

 

AFTER SAMPLE APPROVAL

A. Preproduction       6 PRS 1st week
B. Sample approval and feedback 2nd week
C. Mass production 5-6th week
D. Shipping

Final drawing and expolation dwg
Bom. color chip. Limited sample.

7-8th week
E. Routing order follow-up 6th-7th week

 