we check in trx.MD05,
material :2616260 ,who has the attribute of MRP controller 202
plant: **
An error information shows as below:
User is getting error as mentioned above and hence MRP can not be performed.
1 Solution or Findings
Normally * has practice of changing valid from date of factory calendars.
Here for *– Factory calendar is 99 and valid from year is now changed to 2009

While checking in debug for material 2616260 , it was found that field MDKP-DSDAT
( MRP Date ) is having value as 21.03.2008 which lies before valid from year of factory calendar ( 2009).
31.03.2008 is calculated as 21.03.2008 + planned del time ( 10 days for 2616260 )
As a workaround solution :
We need to temporarily shift factory calendar 99 backwards and do the MRP run for all mentioned materials.
After MRP Run , field MDKP-DSDAT will get updated with new MRP Run date.
Then shifting valid from year of factory calendar 99 back to original.
For this need confirmation from responsible person.